Group Meeting
- finish building the infrastructure for the two sausage system - test the entire system together at once - water pasteurization section...
Group Meeting
- Finished second solar sausage - acquired charge regulator, battery, and fan for energy storage system - ME's finalized work on pressure...
Group Meeting
-order water pump -check on 2nd ME order -Contacat Academy Sports about aerator pumps for pressure regulator - Solar panels : have to use...
Group Meeting
- drop off materials at Ians lab on main campus - EE start building second sausage - ME start putting together pressure regulators -...
Milestone 5 Demo
- presentation in Keen basement on main campus - show Dr. Frank and Dr. Devine the built solar sausage and pressure regulator design -...
Group Meeting
. next milestone due next week, figure out what to present - talk to Ian Winger about using lab for demonstration . ordering process for...
Presentation
-get together and practice early - got email from Dr. Ordonez, himself and Dr. Edrington can not make the presentation (record it) - went...
EE Meeting
milestone 4: - go over each component . design . test plan . overall compilation into total system - make sure report flows -compile ME...
Dr. Frank Meeting
. talk briefly about upcoming milestone . making sure the mixed department team is working well together . talk about more efficient...
Group Meeting
Schedule Presentations . Milestone 4: February 13, 2015 @3pm . Milestone 5: February 27, 2015 @ 1:30pm . Milestone 6: April 10, 2015 @...