Group Meeting
- solarsausageteam26
- Apr 14, 2015
- 1 min read
- finish building the infrastructure for the two sausage system
- test the entire system together at once
- water pasteurization section is failing
-first power output tests are low
- as we were able to perfect the focal point of the sausage the power output increased immediately
*****Our final system testing was done a week later and our final power output was 40W compared to the 10W we erroneously calculated during initial testing.